Kings Crescent Estate

 

Details

 
AJS were delighted to be awarded a new contract to undertake the upgrade of Lateral and Rising Electrical mains and communal lighting to over 14 blocks on the Kings Crescent Estate, works commenced in November 2011 and completed in August of 2012.
 
Client: Hackney Homes
Value: £630000
Duration: 11 Months
 
Contact Us
 
 
     
 
 

Scope Of Work

 
bullet Modifications to convert the existing Wet Riser back to a Dry Riser
   
   
bullet Dismantling and Removal of Riser Water Tank
   
   
bullet Removal of water Tank Piers and Bunded Area Clearance
   
   
bullet Fire Alarm Installation
   
   
bullet Forming and screeding tank room floor
   
   
bullet Removal of existing hydrant pumps and controllers
   
   
bullet Installation of suction and delivery pipework
   
   
bullet Installation of Panel board/ Distribution Units and various sub circuits
   
   
bullet Replacing landing valves with regulating valves
   
   
bullet Testing and Commissioning
   
   
bullet All works carried out whilst residents were in occupation
   
   
 
     
     
   